by Sarah Chughtai | Mar 2, 2026
81 Bay, a monumental, forty-nine storey, office and retail development in downtown Toronto was built leveraging EXACT’s state-of-the-art temperature, strength and formwork monitoring technology. The project had very demanding requirements in terms of concrete design....
by Kaitlyn Callow | Sep 28, 2025
Exact Scope On-site climate control using 150 kW & 60 kW electric heaters, with targeted monitoring and control across floors at different stages of completion. Project Objectives, Requirements & Challenges Mass timber builds are highly sensitive to...
by Kaitlyn Callow | Sep 28, 2025
EXACT Technology Corporation monitored the concrete temperature in several locations of this raft slab pour to help the project team proactively meet the mass concrete requirements for maximum temperature and allowable differentials. June 3, 2021 We’ve helped the team...
by Kaitlyn Callow | Sep 28, 2025
EXACT SCOPE: Strength and temperature monitoring for critical cast-in-place concrete elements across all 39 floors to optimize formwork cycling, accelerate construction timelines, and ensure adherence to the ambitious project schedule. Highlights: Toronto’s 125 George...