Project Objectives, Requirements & Challenges
Kiewit was tasked with a monumental engineering feat: making a decades-old bridge earthquake-ready. The project, the largest in Oregon in 45 years, required the construction of new foundations, columns, and crossbeams cast around existing elements to reinforce the structure.
Key Challenges and Requirements:
- Seismic Retrofit Complexity: The most significant engineering challenge was making the existing, decades-old structure earthquake-ready while maintaining its operational integrity.
- Mass Concrete Management: New foundations, columns, and crossbeams often involving mass concrete pours, required strict thermal control to prevent cracking and ensure long-term durability. Traditional methods, such as cooling tubes, are labor-intensive, costly, and can introduce additional safety risks.
- Accelerated Schedule Demands: Critical operations like post-tensioning, form removal, and construction loading required reliable, timely verification of concrete strength to maintain the ambitious project schedule. Delays due to conservative strength estimates or time-consuming traditional testing would significantly impact the overall timeline.
- Compliance and Quality Assurance: The project required adherence to specifications, including ACI best practices, and meticulous documentation for quality assurance submissions.
- Cost & Resources Efficiency: A major goal was to save time and money by eliminating traditional cooling tubes in almost all pours. The opportunity to implement a Performance-Based Temperature Differential Limit (PBTDL) instead of the traditional fixed maximum temperature differential required a robust, reliable, and real-time monitoring solution that allowed them to end thermal control earlier which saved time and resources on-site.

Meeting the Challenge: Kiewit’s Use of EXACT Technology
To meet the engineering challenges, demanding schedule, and strict quality requirements, Kiewit leveraged the EXACT system for a comprehensive, data-driven approach to concrete management.
EXACT Offerings Utilized:
- EXACT Monitor: Used for real-time monitoring of thermal control/mass concrete, maturity for construction loads, and cold weather protection. System alerts were set up to prevent temperature differentials from being exceeded.
- EXACT Match: EXACT Match was used to perform an additional validation of the maturity curve. Cylinders were cured at the same temperature as the monitored in-situ concrete to verify that predicted maturity matched actual compressive cylinder break data.
- Maturity: Enabled the use of maturity curves to verify concrete strength for releasing falsework and commencing post-tensioning, optimizing the construction schedule.
- PBDTL Ready: Provided the necessary real-time data and tracking capabilities to execute Kiewit’s PBTDL engineering and thermal control plan, replacing traditional fixed T-diff limits.
Utilizing the EXACT System for Precision and Quality
1. Real-Time PBTDL Management and Thermal Control: Kiewit’s decision to use a PBTDL instead of a traditional fixed maximum temperature differential was critical for project efficiency and cost savings. This approach, however, necessitates precise temperature monitoring. The EXACT Monitor system was used to read and react to the in-field situation and live data, continuously calculating current strength, tracking current temperature differentials (Tdiffs), and sending out real-time alerts when conditions approached the pre-set safety factor.
“Managing a PBTDL curve without a system like EXACT would have required significantly more effort. The system does the heavy lifting… sending out alerts when something in the field needs to change to keep the element in spec.” – Benjamin Moseid, Quality Manager
2. Optimizing the Schedule with Maturity Data: By allowing the use of a maturity curve to validate strength, the EXACT system provided a significant schedule advantage. Instead of waiting on conservative time-based estimates or slower lab breaks, the team had real-time strength data available at the tip of their fingers. This allowed for immediate verification of strength needed for releasing falsework, construction loads, and commencing post-tensioning, directly optimizing the schedule for critical concrete operations.
3. Maturity Curve Validation with EXACT Match: To ensure maximum confidence in the maturity data, Kiewit performed an additional validation on the post-tensioning concrete mixes. The EXACT Match curing chamber was linked to an in-field sensor, heating the cylinders to the exact same temperature as the monitored in-situ concrete. Compressive breaks on these cylinders validated that the concrete in the field had achieved the required strength.
4. Data Reliability and System Flexibility: One key advantage was the EXACT system’s database approach. Unlike other systems that discard data outside of the immediate monitoring period, EXACT saves all data in the cloud, ensuring it is never lost and is available for transparent management, and easy quality assurance reporting.

Project Outcomes
By leveraging the full capabilities of the EXACT system, Kiewit achieved significant quality, safety, and efficiency gains on the Abernethy Bridge project.
- Real-Time Monitoring During Cooling: Kiewit used cooling tubes on almost every pour, and the PBTDL let the team monitor concrete temperatures throughout those operations.
- Quality & Safety: Many real-time alerts sent during column work prevented temperature differentials from being exceeded, ensuring quality. Adjusting the PBTDL safety factor based on crew availability and proximity ensured team safety and prevented potential quality incidents.
Real-Time Data Drives Critical Decisions
The investment in developing the PBTDL and using the EXACT system to manage it was well worth it. This process was a necessity, saving significant time and money. The real-time data and intuitive system allowed Kiewit to properly manage thermal control, react before issues became a quality concern, and provide transparent information to the client.
The PBTDL and EXACT system directly addressed the challenge of reinforcing existing structures with new elements, as reducing the amount of work to do (i.e., eliminating cooling tubes) reduced cost and eliminated the safety incidents that could have happened while performing that work on the new columns and crossbeams. Furthermore, EXACT made exporting the required final quality assurance reports quick and easy.
“I am most proud of the team of builders we have taught critical lessons that will enhance the rest of their careers. The lessons they have learned in safety, quality, and production will help them be team builders here and in the future.” – Benjamin Moseid, Quality Manager
In Conclusion
The Abernethy Bridge project is a testament to Kiewit’s commitment to innovation and how a high-quality, flexible monitoring system like EXACT can elevate large-scale infrastructure projects. As the project rolls into its final phases, superstructure widening, bearing replacement, and bridge translation, the fundamental lessons learned in utilizing PBTDL and real-time data will be carried forward.
The Abernethy Bridge project validates that managing a PBTDL curve with a system like EXACT is not only possible but required to save significant time and money compared to traditional methods, setting a new standard for infrastructure construction.