Heat, Speed and Strength: Electrifying Finfrock’s Precast Curing Process

The Project

Location: Apopka, Florida
Client: FinFrock
Project Timeline: September 2024 through Summer 2025
EXACT Solution: xControl
In February 2025, EXACT’s xControl team completed a two-week installation of an electric curing system on Finfrock’s existing 384-foot double tee beds in Apopka, Florida.  This project, which began in planning stages back in September 2024 and was commissioned in summer 2025, marks another milestone in the ongoing relationship between EXACT and Finfrock. By retrofitting electric heating onto existing formwork, EXACT enabled Finfrock to modernize operations with minimal disruption and extend the value of their previous investments. The installation was efficient, collaborative, and the results provided an electric heating solution over other mediums of heat.

Over the course of two weeks, the team installed a total of 540MI and 16 Nichrome heaters – across 18 bed sections, using over 2,000 weld studs. Thanks to labeled wiring harnesses, pre-positioned weld clips, and efficient planning, the retrofitting process was smooth and accelerated each day. Having welders on standby ensured any unexpected repairs could be managed instantly. Behind the scenes, EXACT’s production, operations, and procurement teams played a critical role in delivering the right components on time, including last-minute needs.

The real win, however, was strategic: retrofitting Finfrock’s existing forms with EXACT’s electric curing system gave them a powerful modernization tool without the cost and disruption of replacing infrastructure. This upgrade allows Finfrock to apply controlled heat to the concrete curing process, enabling faster form stripping and more consistent early break strength results.

The project was a technical and logistical success. Not only was the job completed efficiently, with daily improvements in process and pace, but the results promise long-term value. The electric curing system will improve production output and consistency at Finfrock, helping them stay competitive while maximizing the use of their existing forms. These two curing beds are just the latest in a growing list of EXACT installations for Finfrock, reaffirming a trusted partnership built on reliability, innovation, and high performance.

 

High-Rise / Institutional

  • Strip Earlier
  • Avoid Rework
  • Meet Scheduled Targets

Infrastructure

  • Monitor Mass Concrete
  • Meet DOT Specs
  • Verify Results

Precast/Prestressed

  • Turn Beds Faster
  • Optimize Labor
  • Digitize Production and QC

Testing Labs

  • Differentiate Your Business
  • Automate Reporting
  • Land More Projects

Partners

  • DOTs & Inspectors
  • Engineering Consultants
  • Strategic Partners

Cast-in-Place Solutions

From infrastructure to high-rise, EXACT combines monitoring, match-curing, and digital tracking to help contractors pour smarter, strip sooner, and deliver stronger, more reliable structures with confidence.

Precast / Prestressed Solutions

EXACT’s integrated monitoring, match curing, control and digital tracking solutions give precast/prestressed producers end-to-end visibility that accelerates cycles, reduces costs, and improves quality.

Concrete Testing Solutions

EXACT’s monitoring and match-curing solutions give labs accurate, trusted results with streamlined workflows and digital records that reduce delays, cut manual effort, and strengthen client confidence.